Capital Improvement Projects

Look here to find information on current projects happening in our community to enhance your water service. 

 

2018 Projects

Ring & Buchanan Road Improvements – This project consists of replacing approximately 6,800 linear feet of 2” water main with 8” and 4” water mains to improve service to customers on Ring and Buchanan Roads. This project is ready to bid and it has been scheduled on the CIP to receive bids in January 2018.

2017 Projects

FM 664 Improvements 24” Water Main Phase 1 – This project consists of replacing the 12” water main coming east out of Plant 2 McKenna with a new 24” water main to serve Camden Park (under construction), a new nursing home and additional demands in the Plant 2/Ferris service area. Circle H started at Plant 2 and was laying 24” main about 300’ east on Thursday, April 13th.

 

FM 664 12” Extension for Dollar General – This project consists of 1,600 linear feet of 12” water main extension along the north side of FM 664 from Pratt Road easterly to the existing 6” main that crosses to the south side of FM 664. Bids were taken on April 12, 2017, and Circle H Contractors was the low bid. We have scheduled a Pre-Construction Conference for April 18th at 1:30pm. One easement remains to be acquired.

Bond Projects

Phase 10 – Kristen Elevated Storage Tank – This project consists of replacing the 0.5 MG Elevated Storage Tank at Plant #8 with a new composite 2 MG Elevated Storage Tank at Kristen Pump Station All paint should be complete by April 27th. Circle H should start the yard piping by April 27th and be complete by May 21st. Landmark’s contract time is up November 6, 2017 and their current schedule shows project completion by August 1st.